Skip to main content

Service Impacts

Service Outages & Impacts
Location Area Start Finish Repair Type Repair Description Service Impact Type Contact Person Contact Phone

Wye Oak Building, Exterior Window Cleaning Wye Oak Building 07-30-2026 8:00 am 07-30-2026 3:00 pm Cleaning exterior windows Window cleaning will be performed for all exterior windows. Planned Makisha Thomas 301-405-2222
Marie Mount Hall, Exterior Window Cleaning Marie Mount Hall 07-29-2026 8:00 am 07-29-2026 3:00 pm Cleaning exterior windows Window cleaning will be performed for all exterior windows Planned Makisha Thomas 301-405-2222
Shoemaker Building, Electrical Outage Shoemaker Building 07-25-2026 6:00 am 07-25-2026 3:00 pm Electric Outage safely perform required preventive maintenance on the buildings medium voltage transformer and switch. Planned Jason Pearson 301-405-2222
Chemistry Building, Interior Window and Glass Cleaning Wing 1 Areas in Floors 1 - 3 07-23-2026 8:00 am 07-24-2026 4:00 pm Interior Window Cleaning window and glass cleaning will be performed at the Chemistry Building of interior windows and glass in wing 1, which will include the conference rooms, workstation glass on floors 1 through 3, and the center stairwell glass. Planned Makisha Thomas 301-405-2222
Memorial Chapel, Exterior Window Cleaning Memorial Chapel 07-15-2026 8:00 am 07-15-2026 1:00 pm Cleaning exterior windows Window cleaning will be performed for all exterior windows Planned Makisha Thomas 301-405-2222
Physical Sciences Complex, Interior and Exterior Glass Cleaning First Floor Main Lobby, Facing the Atrium 07-14-2026 8:00 am 07-14-2026 1:00 pm Exterior and Interior Window Cleaning A scheduled interior and exterior glass cleaning will be performed for the first floor main lobby, facing the atrium Planned Makisha Thomas 301-405-2222
Exterior South of Shoemaker Building - Dumpster Placement for LeFrak Hall Playground Renovation **SEE MAP ATTACHED** 07-13-2026 7:00 am 07-24-2026 3:00 pm Dumpster Placement, Renovation Work To demolish and replace playground equipment at the LeFrak Hall playground, there will be a placement of a dumpster to the exterior south of the Shoemaker Building for the removal of the demolished playground equipment. Planned Anthony Brown 301-405-2222
Reckord Armory - Lift Work, Roofing Repair Work Reckord Armory, northwest sidewalk facing Clarence M. Mitchell Jr. Building 07-13-2026 6:00 am 07-15-2026 3:00 pm Lift Work, Roof Repair Repair a section of the roof that leaks Planned Colin Davis 301-405-2222
Mowatt Lane Parking Garage, Electrical Outage Mowatt Lane Parking Garage 07-11-2026 6:00 am 07-11-2026 3:00 pm Electric Outage Required preventive maintenance on the buildings medium voltage transformer and switch Planned Jason Reardon 301-405-2222
Millard and Joseph Tydings Hall, Interior Building Closure Women's Restroom 0125 **SEE MAP ATTACHED** 07-10-2026 7:00 am 07-17-2026 5:00 pm Interior Building Closure Facilities Management Department of Operations, Maintenance, and Utilities will perform an interior building closure of women's restroom 0125 at the Millard and Joseph Tydings Hall for plumbing repairs. Planned Rita Wills 301-405-2222
Central Energy Plant, Service Building - Domestic Cold and Hot Outage Entire Building(s) 07-10-2026 6:00 am 07-10-2026 10:00 am Domestic Hot and Cold Water Outage Due to a defective domestic water isolation valve at the Central Energy Plant, Facilities Management responders will need to perform an urgent domestic hot and cold water outage that will impact sinks, toilets, drinking water, and showers. Planned Randall Phillips 301-405-2222
Biomolecular Sciences Building, Natural Gas Outage and Domestic Water Outage Rooms 1104 and 1106 ONLY 07-10-2026 6:00 am 07-10-2026 2:00 pm Natural Gas Outage and Domestic Water Outage Install natural gas and domestic hot and cold water connections for a new fume hood and eyewash station Planned Teon Saunders 301-405-2222
Urgent Outage Notification: Turfgrass Research Facility, Electrical Outage Entire Building. 07-09-2026 10:06 pm Electrical Outage Facilities Management crews are responding to an urgent PEPCO-related electrical outage impacting the Turfgrass Research Facility due to weather-related impacts. PEPCO responders are on-site working to restore power. Unplanned Brian Trest 301-405-2222
Urgent Outage Notification: 4-H Headquarters, Electrical Outage Entire Building. 07-09-2026 6:38 pm Electrical Outage Facilities Management crews are responding to an urgent PEPCO-related electrical outage impacting 4-H Headquarters due to weather-related impacts. Unplanned Robert Hermstein 301-405-2222
Urgent Outage Notification: Avrum Gudelsky Veterinary Center, Electrical Outage Entire Building(s) 07-09-2026 6:14 pm Electrical Outage Facilities Management crews are responding to an urgent PEPCO-related electrical outage impacting Avrum Gudelsky Veterinary Center due to weather-related impacts. Unplanned Glynnis Bowman 301-405-2222
Urgent Outage Notification: South Hill Resident Halls - HVAC Chilled Water and Air Conditioning Outage; Washington Quad Excavation Work **SEE MAP ATTACHED** 07-09-2026 8:00 am HVAC Chilled Water Outage, Excavation Work Facilities Management crews are responding to an urgent leak on a dual-temperature line in the Washington Quad area that supplies HVAC chilled water to South Hill Resident Halls for air conditioning and cooling. Emergency Horacio Torres 301-405-2222
South Hill Resident Halls - Multiple Buildings, Domestic Hot Water Outage Harford Hall, Calvert Hall, Baltimore Hall, Cecil Hall, Prince George's Hall, Kent Hall, Talbot Hall, Garrett Hall 07-09-2026 7:00 am 07-09-2026 5:00 pm Domestic Hot Water Outage As part of the work to relocate the domestic hot water and dual temperature water service lines to Baltimore Hall to eliminate water infiltration through the floor of the building, a domestic hot water pipe will need to be replaced at Baltimore Hall. Planned Horacio Torres 301-405-2222
Atlantic Building, Domestic Cold Water Outage Wing 3 of the Building ONLY 07-09-2026 5:00 am 07-09-2026 7:00 am Domestic Cold Water Outage To relocate domestic water piping on the first-floor Quantum renovation in wing 3 of the Atlantic Building, there will be a brief domestic cold water outage that will only impact wing 3 of the building. Planned James Andrews 301-405-2222
Urgent Work Notification: Exterior between Leonardtown Buildings 248 and 249, Emergency Excavation Work, Starting July 8 **SEE MAP ATTACHED** 07-08-2026 6:00 am Emergency Excavation Work Facilities Management crews are responding to an urgent domestic hot water leak occurring in front of Leonardtown Building 249, which will require excavation work to isolate and repair the leak. Emergency Horacio Torres 301-405-2222
Stamp Student Union - Roofing Repair; Union Lane - Partial Roadway Closure Exterior northwest corner and west side of Stamp Student Union (work area marked in blue on the attachment). Union Lane, between Union Lane Parking Garage and Stamp Student Union (closure area marked in red see attachment) 07-07-2026 6:00 am 08-07-2026 6:00 pm Roof Repair Work Roofing replacement and repair work on the building. Planned Raquel Gayle 301-405-2222
Baltimore Hall, Excavation Work North Exterior Side **SEE MAP ATTACHED** 07-06-2026 7:00 am 07-17-2026 5:00 pm Excavation Work To relocate the domestic hot water and dual temperature water service lines to Baltimore Hall to eliminate water infiltration through the floor of the building, excavation work will need to be performed outside of the north side of the building. Planned Horacio Torres 301-405-2222
Urgent Outage Notification: Atlantic Building, HVAC Systems Outage, HVAC Heating Outage Wing 4 of the Building. 06-30-2026 4:07 pm HVAC Systems Outage, HVAC Heating Outage Facilities Management crews are responding to an urgent repair required on the HVAC heating hot water converter that supports equipment responsible for heating service in wing 4 of the Atlantic Building. Planned Gerald Young 301-405-2222
Engineering Annex, Exterior Painting Entire Exterior of Building 06-30-2026 7:00 am 07-17-2026 3:00 pm Exterior painting The contractor will prepare, prime and paint the doors, windows and fascia on all sides of the building Planned Rolando Mendez 301-405-2222
John S. Toll Physics Building, Demolition Work Penthouse Mechanical Room 5300, Loading Dock Area 06-26-2026 7:00 am 07-16-2026 5:00 pm Demolition Work There will be ongoing demolition of mechanical equipment in the penthouse mechanical room 5300 at the John S. Toll Physics Building, related to the NextGen Energy Program. Planned Antonio Sanchez 301-405-2222
Urgent Outage Notification: Manufacturing Building, HVAC Systems Outage North side, first floor of the building **SEE MAP ATTACHED** 06-25-2026 11:50 am HVAC Systems Outage An urgent HVAC systems outage that is impacting HVAC equipment responsible for HVAC air conditioning and cooling for the north side of the first floor at the Manufacturing Building. Unplanned Charles Ivey 301-405-2222
Campus Drive, Sidewalk and Bike Lane Closures Exterior North of H.J. Patterson Hall **SEE MAP ATTACHED FOR ALL CLOSURES, DETOURS** 06-22-2026 6:00 am 08-26-2026 6:00 pm Sidewalk Closure, Bike Lane Closure, Crosswalk Closure To replace approximately 120 feet of steam and condensate piping along the south side of Campus Drive between the northwest corner of HJ Patterson Hall and near the west side of the Edward St John Learning and Teaching Center. Planned Chrysanthe Broikos 301-405-2222
Atlantic Building - Interior Building Closure 4th floor of Wing 3 ***See map attached*** 06-15-2026 5:00 am 07-10-2026 2:00 pm Interior Building Closure Run new chilled water piping from rooftop to chase for 1st floor labs Planned Jim Andrews 443-472-6243
Atlantic Building, Interior Building Closure First Floor of Wing 3 **SEE MAP ATTACHED** 06-08-2026 5:00 am 08-07-2026 2:00 pm Interior Building Closure To allow for duct and sprinkler modifications in this area of the building. Planned James Andrews 301-405-2222
Francis Scott Key Hall, Interior Building Closure Restrooms 0108 and 0112; Dumpster in Lot W1 *SEE ATTACHED MAP* 05-26-2026 6:00 am 08-14-2026 6:00 pm Interior Building Closure To perform ADA upgrades to women's restroom 0108 and men's restroom 0112. Planned Adesanmi Fajemisin 301-405-2222
Edward St. John Learning and Teaching Center, HVAC Chilled Water Outage South and East Ground and First Floor Areas of the Wing 1 *SEE MAP ATTACHED* 05-26-2026 6:00 am 08-14-2026 6:00 pm HVAC Chilled Water Outage To perform renovation and construction work to replace all chilled water pipe insulation in these areas of the building. Planned Adesanmi Fajemisin 301-405-2222
Road Closures
Location Area Start Finish Repair Type Repair Description Service Impact Type Contact Person Contact Phone

Regents Drive - Roadway Closure and Sidewalk Closure; Parking Lot TT - Partial Parking Lot Closure **SEE MAP ATTACHED FOR IMPACTED AREAS, DETOUR** 07-15-2026 7:00 pm 07-17-2026 5:00 am Road Closure, Sidewalk Closure, Partial Parking Lot Closure As part of the NextGen Energy Program, a crane and dumpster will be staged on Regents Drive during overnight hours to remove demolition debris from the rooftop of the John S. Toll Physics Building. Antonio Sanchez 301-405-2222
Purple Line: Campus-wide Periodic Lane and Sidewalk Closures SEE MAP - MULTIPLE LOCATIONS 06-01-2026 7:00 am 08-28-2026 5:00 pm Purple Line Construction Purple Line Construction Planned Casey Ferraro 301-405-9168
Fieldhouse Drive - Sidewalk Closure and Partial Roadway Closure; Parking Lot Z - Partial Parking Lot Closure **SEE MAP ATTACHED** 05-26-2026 7:00 am 07-17-2026 4:00 pm Sidewalk Closure, Partial Roadway Closure, Partial Parking Lot Closure To accommodate work related to the third phase of the Health and Human Sciences Complex construction project. Planned Randall Phillips 301-405-2222
Parking Lot #Z, Partial Parking Lot Closure Southeast corner of the parking lot. 12-22-2025 7:00 am 09-01-2028 4:00 pm Partial Parking Lot Closure To facilitate the construction laydown area for the Health and Human Sciences Complex project. Planned Randall Phillips 443-500-2356
Elevator
Location Area Start Finish Repair Type Repair Description Service Impact Type Contact Person Contact Phone

Urgent Outage Notification: Stamp Student Union, Elevator Outage Elevator Car 5 07-08-2026 7:00 am Elevator Outage Elevator car 5 (passenger elevator) at Stamp Student Union has been taken out of service for emergency maintenance and repairs by Facilities Management responders. Unplanned Shane Kogok 301-405-2222
Ellicott Hall - Elevator 3, Elevator Modernization Elevator 3 04-09-2026 7:00 am 07-13-2026 11:59 pm Elevator modernization This is a planned modernization upgrade of the elevator. Planned Chris O'Dea 301-405-2222
Cumberland Hall, Elevator Modernization Elevator Car #2 02-03-2026 8:00 pm Elevator modernization Modernization of Elevator #2 Planned Chris O'Dea 301-405-2222