Location Area Start Finish Repair Type Repair Description Service Impact Type Contact Person Contact Phone

Severn Building Domestic Hot Water Outage Severn Building 07-11-2024 8:00 am 07-11-2024 10:00 pm Boiler Maintenance for Building Domestic Hot Water Outage for Boiler maintenance Planned Alonzo Banks 301-395-2303
Manufacturing Building, Neutral Buoyancy Research Facility Exterior Painting Exterior 07-08-2024 7:30 am 07-19-2024 3:30 pm Exterior painting Scraping, priming, finishing coat of paint on exterior doors, bollards, rails, and a rollup door Planned Rolando Mendez 301-852-1308
Jimenez Hall North Wing Closure North Wing 3rd and 4th Floors 07-08-2024 7:00 am 07-10-2024 3:00 pm North Wing Closure Abate,emt work/Area Closure Planned Paul Jackson 3014051903
La Plata Hall & Ellicott Hall Electrical/ Elevator Outage La Plata and Ellicott Hall 07-08-2024 7:00 am 07-08-2024 9:00 am "Electric, Elevator, Fire Alarm Test/Sprinkler, Replace Meter Planned Jason Reardon 2406948431
Marie Mount Hall Heating Hot Water Outage Suite 1401 07-08-2024 7:00 am 07-19-2024 2:30 pm Heating Hot Water Outage Replace Control Control Valve Planned Gerald Young II (240) 882-5573
CSPAC Heating Hot Water Outage Building 07-08-2024 7:00 am 07-10-2024 3:30 pm To install two hot water meters for the building. Heating Hot Water Planned Jason Reardon 240-694-8431
Parking Lot #1 and Parking Lot #Z, Partial Parking Lot Closure Specific Parking Spaces within Parking Lot #1, Parking Lot #Z 07-03-2024 6:00 am 07-15-2024 6:00 pm Parking Lot Modifications Modify medians in parking lot to improve vehicular circulation patterns. Planned Chris Tenneson 301-405-8263
H.J. Patterson Roof Work/Lift Work Exterior Sidewalk Closure 07-03-2024 5:00 am 07-04-2024 4:00 pm Lift Repair Roof Repair Planned Colin Davis 301-458-1741
Jimenez Hall Roof Repair/Lift Work Sidewalk Closure 07-02-2024 5:00 am 07-03-2024 4:00 pm Partial Sidewalk Closure Lift Work Planned Colin Davis (301) 458-1741
Thurgood Marshall Hall Sidewalk Closure Exterior Sidewalk Closure 07-01-2024 7:00 am 07-26-2024 6:00 pm Partial Sidewalk Closure Concrete Work Planned Catherine Baugh 3014054673
LeFrak Hall Entrance/Lobby Closure North Entrance 06-24-2024 6:00 am 07-12-2024 5:00 pm Entrance Closure Furr walls/ Install LIghting and Florring Planned Anthony Brown (301) 405-0206
Reckord Armory Sidewalk Closure Exterior Sidewalk Closure 06-24-2024 6:00 am 07-05-2024 2:00 pm Partial Sidewalk Closure Sconce Installation Planned Kenneth Jester (301) 405-7825
Tawes Hall Exterior Painting Exterior 06-13-2024 7:00 am 07-13-2024 5:00 pm Exterior painting Exterior Painting Planned Rolando Mendez (301) 852-1308
Woods Hall Interior Area/Room Closures Ground Floor 06-12-2024 6:00 am 09-24-2024 6:00 pm Interrior Room Closure Ground Floor Renovations Tim Zhao (240) 383-2431
Varsity Sports Team House Entrance/Parking Space Closure Exterior Sidewalk and Entrance Closure 06-03-2024 6:00 am 08-16-2024 5:00 pm Parking Lot Closure Improve Sidewalk Network Planned Chrysanthe Broikos (301) 956-6155
Field House Drive, Alumni Drive at Championship Ln Circle Partial Lane Closure Exterior Roads 05-28-2024 5:00 am 08-18-2024 7:00 pm Partial Road Closure/Sidewalk Closure Install Underground Piping Planned Al Neshati (301) 405-4454
Clarice Smith Performing Arts Center Entrance Closure Music Wing 02-07-2024 12:00 am 07-31-2024 12:00 am Entrance Closure Replace HVAC water lines Planned Stephen Edward Cole (240) 882-6233
Road Closures
Location Area Start Finish Repair Type Repair Description Service Impact Type Contact Person Contact Phone

Stadium Drive, Partial Road Closure Stadium Drive, from Lot R3 eastward to the Atlantic Building 07-05-2024 4:00 am 07-05-2024 9:00 am Street Lighting Removal of street poles for replacements to be installed at a later date. Planned Chrysanthe Broikos 301-935-6155
Partial Road/Sidewalk Closure Campus Drive Campus Drive near Paint Branch Drive 07-01-2024 6:00 am 07-05-2024 6:00 pm Partial Road Closure Excavation and shoring for steam line work Planned Daniel B. Klenner (240) 882-5052
Symons Hall Entrance Closure Campus Drive Side Exterior Sidewalk and Entrance Closure 06-10-2024 7:00 am 08-20-2024 7:00 pm Purple Line Construction Entrance/Sidewalk Closure Planned cferraro@umd.edu (301) 405-9168
C. Daniel Mote, Jr. Engineering Lab & Martin Hall Parking Lot Closure Parking Lot 05-28-2024 6:00 am 08-21-2024 6:00 pm Parking Lot Closure Handicapped Parking Configuration Daniel Klenner (240) 882-5052
Edward St. Johns Learning and Teaching Center Campus Drive Entrance Closure Exterior Roads 05-23-2024 7:00 am 08-20-2024 5:00 pm Partial Road Closure Purple Line Construction Planned Casey Ferraro (301) 405-9168