Skip to main content
Facilities Management
About FM Services Projects & Programs Info & Resources FM Staff Connect
About FM
Our Team Our Units Mission, Vision, Values Strategic Priorities FAQs Recognition News FM Deep Dive Podcast Series Working for FM
Services
Capital Projects Create a New Service/Project Request Fleet Services Housekeeping Services Logistical Services Recycling & Waste Management Photography Services Renovation Projects Signs & Graphics Snow Command Center Request Service Special Services Terrapin Trader Warehouse
Projects & Programs
Arboretum and Botanical Garden Campus Facilities Plan Current Construction Map NextGen Energy Program SHIFT Student Facilities Fund Sustainability
Info & Resources
ADA Transition Plan Building Inventory Design Criteria/Facilities Standards Facilities Archival Library Facility Quick Facts Glossary of Abbreviations & Acronyms OM&U Facility Managers On-Call General Contractor Specs Service Impacts Space Use Change Form UMD Office Standards UMD Spaces
FM Staff Connect
Appreciation & Recognition Calendar Human Resources Tools & Resources Life@FM
Our Team Our Units Mission, Vision, Values Strategic Priorities FAQs Recognition News FM Deep Dive Podcast Series Working for FM
Capital Projects Create a New Service/Project Request Fleet Services Housekeeping Services Logistical Services Recycling & Waste Management Photography Services Renovation Projects Signs & Graphics Snow Command Center Request Service Special Services Terrapin Trader Warehouse
Arboretum and Botanical Garden Campus Facilities Plan Current Construction Map NextGen Energy Program SHIFT Student Facilities Fund Sustainability
ADA Transition Plan Building Inventory Design Criteria/Facilities Standards Facilities Archival Library Facility Quick Facts Glossary of Abbreviations & Acronyms OM&U Facility Managers On-Call General Contractor Specs Service Impacts Space Use Change Form UMD Office Standards UMD Spaces
Appreciation & Recognition Calendar Human Resources Tools & Resources Life@FM

Safety and Notification Requirements

for Construction, Operations, Maintenance, and Utility Work Adjacent to the Purple Line Infrastructure

Contractors must prepare and submit a Track Allocation Permit Request and site-specific safety plan for work in Zones 1, 2, and 3 adjacent to the Purple Line rails and overhead catenary system to the Facilities Management Department responsible for the contractor's work.

Purple Line Adjacent Work Zones
Zone 1 Zone 2 Zone 3
Areas within 10 feet of the OCS and rails Areas > 10 feet and < 25 feet from the OCS and rails Areas >25 feet from the OCS and rails

Minimum Purple Line Track Allocation Permit Request and Site-Specific Safety Documentation Schedule for Submission

  • 21 days: Work in Zones 1 or 2 with no special operation activities
  • 28 days: Work in Zones 1, 2, or 3 involving special operations.

Site Specific Safe Work Plans for Zones 1, 2, and 3 Construction, Operations, Maintenance, and Utilities Work Mandatory Elements

  1. Project or Work Activity Narrative (Description of Planned Site Activities)
  2. Site Footprint, Map, or Sketch showing the Work Zone Perimeter
  3. Zone Specific Controls
    Zone 1 means for protecting/limiting contact or damage to the OCS
    Zones 2 and 3-controls identified to limit work encroachment into Zone 1
  4. For all special operations1 work-include a site-specific safety plan specific to the intended project, e.g., crane lift plane, excavation site plan
  5. Identification of any additional engineering and/or administrative controls to ensure both worker and site safety
  6. Dates for the planned work, name of the contractor(s) and contact name(s) & phone number(s)

Documentation Review, Acceptance, and Transmission Process
Contractor must fill out the Purple Line Track Allocation Permit Request, attached the Site-Specific Safety Plan and submit these documents to Project Manager.  FM Safety & Emergency Management or ESSR Occupational Safety and Health will review the Track Allocation Permit Request, all site safety documentation, prepare and submit the Track Allocation Permit Request, and relay the track allocation permit back to the Project Manager.

1 Special Operations include, but are not limited to:

  • Elevated Working Surfaces
  • Material Handling and Construction Equipment
  • Earthmoving, Construction, and Heavy Landscaping Equipment
  • Occupancy of the Zone 1 area for greater than 15 minutes

 